Recent projects

  • Linton Watercourse and Stormwater Network Realignment

    In 2021 MAP Projects completed a swale diversion project for Linton Military Camp. The diversion was required to enable future vertical construction within the camp. Key to the project was the excavation and shaping of 400 metres of swale nearing five metres deep...

    Read more
  • Ardmore Military Training Area Boundary Fence Upgrade

    In early August 2020 MAP Projects finished the construction of some 13km of deer fencing along the Ardmore Military Training Area (AMTA) boundary and a fully automated gate at the entry to the training facility, for the New Zealand Defence Force.

    This was a project in support of impending statutory requirements for the Auckland Council’s regional pest management plan and to improve security of the training area.

    The area covers a large area of hard, steep terrain that runs through dense bush and the occasional boggy creek...

    Read more
  • Wairakei East Wetland (Pond G) Construction

    MAP Projects was engaged by Tauranga City Council to undertake the construction of stormwater swales and a wetlands area comprising of around 250,00m3 of earthworks and over two kilometres of access track. Culverts in four different locations were installed with a portion of the work, both earthworks and structures, undertaken below the water table.

    This is a large scale project that has run smoothly in consultation with the client and its representatives and where any design issues once encountered have been dealt with in a spirit of mutual cooperation with a view of delivering the best solution within the available budget

    The earthworks comprised of roughly 250,000m3 of sand and topsoil handled and reshaped with 10,000 m3 of fill area...

    Read more
  • Kaituna River Re-Diversion

    MAP was engaged by JSwap Contactors to complete the structures work on the Kaituna River Diversion near Maketu, Bay of Plenty. This involved a large box culvert bridge structure through a body of water, concrete boat ramp, and timber jetties.

    To construct the bridge MAP first installed approximately 250m of sheet pile coffer dam and pumped the work area dry...

    Read more
  • Waitangi Stream Remediation and Erosion Protection

    The Waitangi Stream is controlled by the Bay of Plenty Regional Council and is used to control levels in Lake Ōkāreka. In late 2017 flows were increased beyond the streams capacity causing major scouring of one stream section, putting houses above at risk and damaging the natural environment.

    The site was accessed via a private road which was owned by a number of concerned land owners...

    Read more
  • Omokoroa Stormwater Pond and Earth Dam

    Completed in 2019, the Omokoroa SW Pond 02 for Western Bay of Plenty District Council involved construction of a 9m high by 80m long stormwater detention dam and levelling 5 ha of subdivision lots as the dam fill. The site was large, sloping and involved conditioning various types of soils to enable placing and compacting engineered fill for the Dam embankment and the Classic Builders residential subdivision. Approx...

    Read more
  • Ohinemuri Suspension Bridge

    Built for the Department of Conservation in 2018, this bridge spans 70m across the Karangahake River and weighs a total of 16 tonnes. Made up of six 12 metre long segments, the bridge provided quite a challenge to the construction team.

    The bridge was built alongside the existing suspension bridge which accommodates thousands of visitors annually, working areas were tight, and access to the other side of the river was very restricted...

    Read more