Recent projects
-
Matawii Water Storage Reservoir
Matawii Water Storage Reservoir was constructed by MAP for Te Tai Tokerau Water Trust, with the primary objective of supplying Kaikohe with water for irrigation, which will create sustainable employment opportunities in horticulture and agriculture for the surrounding regions. It will also be back up for clean, reliable drinking water
The reservoir, a zoned embankment structure, stands up to 24 meters high and stretches over 550 meters in length. Given its elevation and proximity to Kaikohe, it is classified as a High PIC reservoir, demanding the highest design, construction, and operational safety standards for the community’s welfare...
-
Esmerelda Street Flood Mitigation
MAP Projects was engaged by Tauranga City Council to complete a fiddly floodwall and flood mitigation project on a negotiated basis. The Esmeralda Flood Mitigation Project involved the placement of some 168m of Redi-rock flood wall up to 4m in height.
The works also included the placement of significant areas of rock protection, stream channeling Gabion baskets and services locations...
-
Nanako Stream Stormwater Upgrade
MAP was engaged by Tauranga City Council in a multi staged ECI with the aim to effectively manage stormwater catchments, mitigate potential flooding events, improve water quality and accommodate future planned developments in the area. The completed B1/2 Separable Portion involved upgrading the existing Kennedy Road embankment to meet current dam safety design standards, reduce the risk of dam failure and provide flood mitigation. The project installed a 2...
-
Waikato River Works
MAP Projects was engaged by Hamilton City Council to complete 3 portions of work on the Waikato River in November 2020
Portion one consisted of the manufacture and install of a steel log deflector to protect Hamilton East bulk water main from river debris. 2x 17m piles were driven from a floating crane into the riverbed to secure the structure. The deflector also served as a new collection point for the irrigation pumps delivering water into the adjacent Hamilton gardens...
-
Linton Watercourse and Stormwater Network Realignment
In 2021 MAP Projects completed a swale diversion project for Linton Military Camp. The diversion was required to enable future vertical construction within the camp. Key to the project was the excavation and shaping of 400 metres of swale nearing five metres deep...
-
Ardmore Military Training Area Boundary Fence Upgrade
In early August 2020 MAP Projects finished the construction of some 13km of deer fencing along the Ardmore Military Training Area (AMTA) boundary and a fully automated gate at the entry to the training facility, for the New Zealand Defence Force.
This was a project in support of impending statutory requirements for the Auckland Council’s regional pest management plan and to improve security of the training area.
The area covers a large area of hard, steep terrain that runs through dense bush and the occasional boggy creek...
-
Wairakei East Wetland (Pond G) Construction
MAP Projects was engaged by Tauranga City Council to undertake the construction of stormwater swales and a wetlands area comprising of around 250,00m3 of earthworks and over two kilometres of access track. Culverts in four different locations were installed with a portion of the work, both earthworks and structures, undertaken below the water table.
This is a large scale project that has run smoothly in consultation with the client and its representatives and where any design issues once encountered have been dealt with in a spirit of mutual cooperation with a view of delivering the best solution within the available budget
The earthworks comprised of roughly 250,000m3 of sand and topsoil handled and reshaped with 10,000 m3 of fill area...
-
Kaituna River Re-Diversion
MAP was engaged by JSwap Contactors to complete the structures work on the Kaituna River Diversion near Maketu, Bay of Plenty. This involved a large box culvert bridge structure through a body of water, concrete boat ramp, and timber jetties.
To construct the bridge MAP first installed approximately 250m of sheet pile coffer dam and pumped the work area dry...
-
Waitangi Stream Remediation and Erosion Protection
The Waitangi Stream is controlled by the Bay of Plenty Regional Council and is used to control levels in Lake Ōkāreka. In late 2017 flows were increased beyond the streams capacity causing major scouring of one stream section, putting houses above at risk and damaging the natural environment.
The site was accessed via a private road which was owned by a number of concerned land owners...
-
Omokoroa Stormwater Pond and Earth Dam
Completed in 2019, the Omokoroa SW Pond 02 for Western Bay of Plenty District Council involved construction of a 9m high by 80m long stormwater detention dam and levelling 5 ha of subdivision lots as the dam fill. The site was large, sloping and involved conditioning various types of soils to enable placing and compacting engineered fill for the Dam embankment and the Classic Builders residential subdivision. Approx...